<listing id="lzpf1"><cite id="lzpf1"><dl id="lzpf1"></dl></cite></listing>
<var id="lzpf1"></var><var id="lzpf1"><strike id="lzpf1"></strike></var>
<menuitem id="lzpf1"><ins id="lzpf1"><strike id="lzpf1"></strike></ins></menuitem>
<var id="lzpf1"></var>
<var id="lzpf1"><strike id="lzpf1"><listing id="lzpf1"></listing></strike></var>
<cite id="lzpf1"><video id="lzpf1"><menuitem id="lzpf1"></menuitem></video></cite><var id="lzpf1"><strike id="lzpf1"><listing id="lzpf1"></listing></strike></var><var id="lzpf1"><strike id="lzpf1"></strike></var>
<cite id="lzpf1"><strike id="lzpf1"></strike></cite>
<var id="lzpf1"><strike id="lzpf1"></strike></var>
<menuitem id="lzpf1"><dl id="lzpf1"><progress id="lzpf1"></progress></dl></menuitem>
<var id="lzpf1"><dl id="lzpf1"><listing id="lzpf1"></listing></dl></var>
<var id="lzpf1"></var>
<var id="lzpf1"></var>
當前位置:

地下管網升級

來源:瀏陽日報 編輯:戴鵬 2021-07-09 10:55:17
微瀏陽
—分享—

01版封面-11.jpg

43號井正在進行掛壁混凝土施工。記者周紅珍

瀏陽日報訊(記者周紅珍)夏日已至,在熱浪中,瀏陽項目建設熱潮涌動。7月7日,記者來到瀏陽市城區生活污水處理提質增效和雨污分流改造項目21號工作井(將軍廣場)施工現場,施工人員正在進行頂管頂進作業。

作為整個項目的重要組成部分,濟川河片區雨污分流工程(將軍廣場至瀏陽河中路段)包含22個頂管井,管線總長度約1800米。自開工建設以來,施工方將該線路分為15個施工點位同步施工。目前,已完成10座頂管井建設,其他井位也正在有序施工中。

現場施工負責人介紹,下階段將進一步加快施工進度,力爭在8月底完成將軍廣場至瀏陽河中路段施工,“濟川河片區雨污分流工程預計在12月底全面完成?!?/p>


來源:瀏陽日報

編輯:戴鵬